Project: Greg's_RV-10   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Greg Kochersperger   -  
Project:   Vans - RV-10
Total Hours:1327.9
Total Flight Time:1.1
Start/Last Date:Jan 15, 2021 - No Finish Date
Engine:IO-540
Propeller:TBD
Panel:Garmin G3X
 
Friendly URL: https://eaabuilderslog.org?s=Greg's_RV-10

Home or Last Project Picture

Oct 09, 2022     Right flap work - (10.5 hours)       Category: 22: Flap
Deburred the remaining skins and spar for the right flap the. Prepped and primed.

10/10: started assembly of the flap bracket assemblies.

10/11: took advantage of my nephew in town and got a lot of work done this evening. Everything dimpled and started riveting the skeleton together.

10/13: finished the skeleton and got the leading edges and top skin cleco'd and set in the cradles.

10/15; got the top and bottom skins riveted and trailing edge taped and cleco'd to the board.

10/17: got it all back-riveted and finished of. Missing two pull rivets.

10/21: got two rivets from another builder. Right flap is done.


 